    Again, Insurgents Cut Power Supply to Maiduguri Towns

    The Transmission Company of Nigeria says insurgents have again vandalised two towers on the Damaturu–Maidugiri 330kiloVolt Transmission Line.

    Mrs Ndidi Mbah, General Manager, Public Affairs, TCN, who said this in a statement in Abuja on Saturday, explained that the two towers were bombed early on Saturday .

    Mbah said that the Saturday vandalism took place after TCN had made concerted effort and restored power to Maiduguri on March 24, two months after the first incident.

    “The incident which occurred at about 5.56 a.m. on March 27 again cut power supply to Maiduguri and its environs.

    ”This time, the insurgents chain bombed two other towers; T152 and T153 on the same line route of the other incident,” she said.

    She, however, said TCN would continue to do all that it could to ensure power supply was restored to the affected areas.

    (NAN)

    Loading

    Spread the love
    Click to comment

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    You May Also Like

    News

    Edo government says it is servicing a monthly Irrevocable standing payment order of ₦385 million for the Radisson Hotel project. Information commissioner Kassim Afegbua...

    News

    Federal Government has announced a nationwide ban on admission and transfer of students into Senior Secondary School Three (SS3), effective from the 2026/27 academic...

    News

    Union Bank of Nigeria has been named Best Company in Workplace Practice at the 2025 Sustainability, Enterprise and Responsibility Awards (SERAS), held at the...

    News

    Economic and Financial Crimes Commission (EFCC) has commenced investigations into a suspected Ponzi scheme operated by a purported real estate firm which allegedly defrauded...